Stage 1 — Design & partners
Engage designer/architect → our joinery team details → coordinate fire engineer → submit DA (with heritage approval if needed). Typically 4–8 weeks.
Stage 2 — Build & install
Workshop build (6–8 wks) → strip-out & base works → joinery install (2–3 wks) → paint/finish → hardware. Typically 8–12 weeks.
Stage 3 — Handover & open
Building compliance → fire inspection → (food) health inspection → pre-open clean → soft furnishings. Usually 2–3 weeks after joinery.
Timeline summary
Total ~16–26 weeks (4–6 months). A full fitout with DA is 2–3× a home job; start planning 6+ months out.